지연¶
Odoo’s Manufacturing app displays delays in manufacturing orders through the Delayed Productions filter. If the MO’s end date exceeds its deadline, the deadline is highlighted in red to draw attention to the delay.
마감일 계산¶
The MO deadline depends on how the MO was created, and is calculated as follows:
Make To Order: the MO deadline is the Sales Order Delivery Date.
Replenishment: the MO deadline is today + Manufacturing Lead Time.
수동 생성된 제조지시서: 마감일 필드는 비어 있습니다.
중요
The MO deadline is not the same as the MO end date.
종료일은 다음과 같이 계산됩니다:
필터¶
지연 상황을 추적할 수 있도록 몇 가지 추가 필터를 활용합니다:
Delayed Productions: the MO’s scheduled start date is later than the deadline.
Late: the MO’s scheduled end date exceeds the deadline, highlighted in red.
Late Availability: one or more required components are not available before the deadline. For example, a confirmed purchase order or manufacturing order for components is scheduled to end after the MO deadline.
구성품 준비 완료: 생산을 시작할 수 있도록 구성품이 모두 준비됨.
사례 검토¶
마감일이 9월 17일 인 MO 를 확인해 보세요:
If production on the MO starts after September 17th, it appears in the Delayed Productions filter.
If required components are scheduled to arrive after September 17th, the MO appears in the Late Availability filter.
If the MO has a scheduled end date after September 17th, it appears in the Late filter.
By combining these indicators, planners can quickly identify where production is at risk of missing delivery commitments.