Bỏ qua để đến Nội dung
Menu
Câu hỏi này đã bị gắn cờ
4281 Lượt xem

When SO is confirmed with due date set to next month (for example) Procurement is generated PO with earliest possible date (today + supplier lead). I'm expecting procurement date as late as possible: SO due date - supplied lead time.

Having a lot of SO confirmed to a 1st day of each month is leading to massive purchase scheduled to beginning of the year instead of gradual spread across the year.

I was trying to find scheduler range days parameter which was stated in v7 doc but had no luck.

Product is MTO, reordering rules are set, no realtime scheduler.

Ảnh đại diện
Huỷ bỏ
Bài viết liên quan Trả lời Lượt xem Hoạt động
2
thg 3 16
9514
1
thg 11 24
4268
0
thg 9 22
1692
1
thg 3 15
5341
0
thg 3 15
4118