Přejít na obsah
Menu
You need to be registered to interact with the community.
This question has been flagged
4285 Zobrazení

When SO is confirmed with due date set to next month (for example) Procurement is generated PO with earliest possible date (today + supplier lead). I'm expecting procurement date as late as possible: SO due date - supplied lead time.

Having a lot of SO confirmed to a 1st day of each month is leading to massive purchase scheduled to beginning of the year instead of gradual spread across the year.

I was trying to find scheduler range days parameter which was stated in v7 doc but had no luck.

Product is MTO, reordering rules are set, no realtime scheduler.

Avatar
Zrušit
Related Posts Odpovědi Zobrazení Aktivita
2
bře 16
9522
1
lis 24
4277
0
zář 22
1693
1
bře 15
5342
0
bře 15
4121