Skip to Content
Menú
This question has been flagged
4217 Vistes

When SO is confirmed with due date set to next month (for example) Procurement is generated PO with earliest possible date (today + supplier lead). I'm expecting procurement date as late as possible: SO due date - supplied lead time.

Having a lot of SO confirmed to a 1st day of each month is leading to massive purchase scheduled to beginning of the year instead of gradual spread across the year.

I was trying to find scheduler range days parameter which was stated in v7 doc but had no luck.

Product is MTO, reordering rules are set, no realtime scheduler.

Avatar
Descartar
Related Posts Respostes Vistes Activitat
2
de març 16
9428
1
de nov. 24
4187
0
de set. 22
1632
1
de març 15
5253
0
de març 15
4065