I cannot explain the meaning of the color orange. I think I understand that red one is that the task allocated time has been arrived or exceeded, and the green one that the task still has more hours available. However, I have doubts about orange one. Is there a relationship with the employee's planned working time?


Thanks in advance

Ảnh đại diện
Huỷ bỏ
Câu trả lời hay nhất

Hi,

The meaning of Orange color is that 

for example if a task allocated hours is 30 hours and a employee spent 24:10 hours

There is Progress bar on the right side of the allocated hours if the Progress bar reach above 80% the orange color appears in your timesheet module.

If the progress bar is 80% it wont show the orange color.


Regards

Ảnh đại diện
Huỷ bỏ
Tác giả

Thank you so much, it was very helpful your answer.