I cannot explain the meaning of the color orange. I think I understand that red one is that the task allocated time has been arrived or exceeded, and the green one that the task still has more hours available. However, I have doubts about orange one. Is there a relationship with the employee's planned working time?


Thanks in advance

Avatar
Abbandona
Risposta migliore

Hi,

The meaning of Orange color is that 

for example if a task allocated hours is 30 hours and a employee spent 24:10 hours

There is Progress bar on the right side of the allocated hours if the Progress bar reach above 80% the orange color appears in your timesheet module.

If the progress bar is 80% it wont show the orange color.


Regards

Avatar
Abbandona
Autore

Thank you so much, it was very helpful your answer.