How can i display Gantt info in the project task ( project module) , add start date and end date for  tasks


Ảnh đại diện
Huỷ bỏ

To increase the interest in your question improving the response potential, it would be good to better elaborate the question, for example: How can I access Gantt view in project v14?

Tác giả

Actually,i m in entreprise version, free trial

Câu trả lời hay nhất

In Project v13 the View Gantt was available and by activating the developer mode, inside Task > Extra Info it was possible to add a "Start date" and "End date".

Unfortunately, in v14, the Gantt functionality  is no longer available in the Project App and requires the Planning App, which has undergone major improvements, including integration with the Project app!

BR

Ricardo

Ảnh đại diện
Huỷ bỏ
Bài viết liên quan Trả lời Lượt xem Hoạt động
2
thg 4 25
1032
1
thg 6 23
3518
1
thg 11 22
3808
Cannot create task Đã xử lý
2
thg 6 20
4006
2
thg 7 18
7539