Ir al contenido
Menú
Se marcó esta pregunta
1 Responder
4540 Vistas

How can i display Gantt info in the project task ( project module) , add start date and end date for  tasks


Avatar
Descartar

To increase the interest in your question improving the response potential, it would be good to better elaborate the question, for example: How can I access Gantt view in project v14?

Autor

Actually,i m in entreprise version, free trial

Mejor respuesta

In Project v13 the View Gantt was available and by activating the developer mode, inside Task > Extra Info it was possible to add a "Start date" and "End date".

Unfortunately, in v14, the Gantt functionality  is no longer available in the Project App and requires the Planning App, which has undergone major improvements, including integration with the Project app!

BR

Ricardo

Avatar
Descartar
Publicaciones relacionadas Respuestas Vistas Actividad
2
abr 25
1070
1
jun 23
3538
1
nov 22
3841
2
jun 20
4047
2
jul 18
7574