İçereği Atla
Menü
Bu soru işaretlendi
1 Cevapla
4426 Görünümler

How can i display Gantt info in the project task ( project module) , add start date and end date for  tasks


Avatar
Vazgeç

To increase the interest in your question improving the response potential, it would be good to better elaborate the question, for example: How can I access Gantt view in project v14?

Üretici

Actually,i m in entreprise version, free trial

En İyi Yanıt

In Project v13 the View Gantt was available and by activating the developer mode, inside Task > Extra Info it was possible to add a "Start date" and "End date".

Unfortunately, in v14, the Gantt functionality  is no longer available in the Project App and requires the Planning App, which has undergone major improvements, including integration with the Project app!

BR

Ricardo

Avatar
Vazgeç
İlgili Gönderiler Cevaplar Görünümler Aktivite
2
Nis 25
870
1
Haz 23
3405
1
Kas 22
3701
2
Haz 20
3899
2
Tem 18
7426