When we start the procurement manually (Version 7), the dates of all quotations are set to today.

But what we want is, to set the date to "start of production - delivery time - security days".

We don't want to fill our warehouse in next days (today + delivery time), when the production of the product is going to start in a year ...

Is it a bug or what are we doing wrong?

Thanks!