Ir al contenido
Menú
Se marcó esta pregunta

Hi!

When we start the procurement manually (Version 7), the dates of all quotations are set to today.

But what we want is, to set the date to "start of production - delivery time - security days".

We don't want to fill our warehouse in next days (today + delivery time), when the production of the product is going to start in a year ...

Is it a bug or what are we doing wrong?

Thanks!

Avatar
Descartar
Publicaciones relacionadas Respuestas Vistas Actividad
5
ene 24
12920
1
mar 15
4620
4
mar 15
29381
1
mar 23
23678
1
jul 16
11238