Lead times can be set at routes->rules and control points at operations.

How can I configure a quality control where I have to wait a certain period of time for the result before the next triggered move?

Avatar
Discard
Author Best Answer

- Create "Quality Control" Locations based on quality control approval times
- Create routes with rules for products/Product Categories that must go to these locations
- Create a Control point type instructions for the operation that moves the products to these locations, at which time samples are taken
- In the rule that moves the product from QC locations to "stock", add a Lead Time as the approval times
- Add a Control point of type pass/fail in the operation that moves the products from the QC locations to the stock