Hi, I have created a project template with the different tasks and sub tasks. 

Is there a way to assign the number of days per task and once a new project is created with this template, and a start day defined, for Odoo to automatically add start and finish dates per task? 

I want to be able to see in the schedule view all start and end dates of the different projects and their activities.

Thanks!