Hi OpenERP community,

I'm actually working on the project management module. After a few try, i want to do something like the example below :

Phases 1 'High Level Analyse' (begin on the 09/09 and end on the 09/10

  • Task 1 : analyse of africa's sheep...

Phases 2 'Spectific Analyse' (begin on the 12/10 and end on the 12/12

  • Task 1 : analyse of africa's sheep...

Imagine that your manager would like to have a first 'analyse' in two weeks. After that, when he have validated this first step, you proceed a second analysis, but now more specific (on the same topic).

I'll know if it's possible to have a "Task 1" who will be shift in the second phase at the end of the first phase ? Or should I create a "Task 1" for all the phases of the project ?

Thank you,

PS : Hope that my english is comprehensible :)

Ảnh đại diện
Huỷ bỏ
Bài viết liên quan Trả lời Lượt xem Hoạt động
1
thg 6 23
3496
1
thg 11 22
3787
Cannot create task Đã xử lý
2
thg 6 20
3979
2
thg 7 19
2644
2
thg 7 18
7525