Hi,

When Odoo 11 was presented by Fabienne you could see on project´s overview a comparision called "timesheet/forecast". I have created a project, I have made forecasts and I have added worked hours. But I can´t see this part of the report. I´m working with Odoo Enterprise

What should I do to see it?

Ảnh đại diện
Huỷ bỏ
Tác giả Câu trả lời hay nhất

I have found it. I have had to do a sale order, and the sale order has ceated a task. On this project, I can see that information.