Skip to Content
Menu
This question has been flagged
1 Reply
2763 Views

My work Orders' scheduled date is before the ordered date, How does this happen?


I changed all my Supplier Lead Times to 0 days

My manufacturing Lead Time is 3 Days

My Customer Lead Time is 7 Days..


This is reflecting in my Stock Journal as well.. MASSIVE problem.. Its the 9th month, and some are showing 8th month.


Please tel me how to fix this

Avatar
Discard
Author Best Answer

I solved this by making

manufacturing Lead Time is -3 Days

&

My Customer Lead Time is -7 Days..


Work fine now..

Avatar
Discard
Related Posts Replies Views Activity
1
Oct 24
127
1
Jul 24
343
2
Feb 24
2945
2
Feb 24
821
1
Jan 24
510