My work Orders' scheduled date is before the ordered date, How does this happen?


I changed all my Supplier Lead Times to 0 days

My manufacturing Lead Time is 3 Days

My Customer Lead Time is 7 Days..


This is reflecting in my Stock Journal as well.. MASSIVE problem.. Its the 9th month, and some are showing 8th month.


Please tel me how to fix this

Avatar
Vazgeç
Üretici En İyi Yanıt

I solved this by making

manufacturing Lead Time is -3 Days

&

My Customer Lead Time is -7 Days..


Work fine now..