Skip to Content
Menu
This question has been flagged
2597 Zobrazenia

Doing some testing with our inprocess implementation.  We have a metal part that we sell that is purchased from a fabricator, 3 week lead time.  We receive the parts then ship them to a subcontractor to be painted with a 2 week lead time.  Once received back from our painting subcontractor we finish package, we allocate 1 week for this.

BOM

We'd like to try using MPS to forecast and schedule orders.  However it seems that the MPS will not work with a BOM type of Subcontract.  

Exception

Additionally our order quantities from our fabricator must be in quantities of 240pcs

Is there a way to allow the MPS scheduler to also work with subcontract BOMs?

Avatar
Zrušiť
Related Posts Replies Zobrazenia Aktivita
2
jún 23
3804
1
feb 22
2404
1
jan 24
5313
0
aug 24
1444
1
nov 21
7074