I used to set the planned start and end date from the EXTRA INFORMATION tab at v13 so I could visualize them.

These fields are not in the EXTRA INFORMATION tab at v14.

How can I visualize my Tasks on the Gantt then?

Avatar
Zrušiť
Best Answer

1. Visit the Project --> Tasks Menu and switch to the Gantt View.


2. Click at the top of a day to see the popup Menu that allows you to Plan existing Tasks.



3. Find  the  Task  you  want  to  plan and open it to add it to the day:



4. You use the handles to drag the Task to the left or right to change the start and end.  If the Task takes several days, leave the Gantt set to show a Week at  a  time.   If it takes several weeks, set the Gantt to show a Month at a time.   if it takes less than a day, set the Gantt to show a Day at a time:

 

Avatar
Zrušiť

@Ray,
Isn't there a way to show the existing planned_start_date and planned_end_date field on the tasks?

Yes, you add them to the View where you want to see them, we have done this by default at version 15 on the Task Form View.