Skip to Content
Menu
This question has been flagged

We have the correct configuration in Odoo 8 that supports the flow Sale Order - Manufacturing Order.

i.e. After confirming a sale order (SO) manufacturing orders (MO) are correctly created and processed.

The MO was for a product that has muti-level BOM. One of the child BOM's has a production location at a subcontractor (supplier)We have the correct routings and a child MO is created for production at the subcontractor.

A stock move issues the products in the child BOM for delivery to the subcontractor.

My client also wishes the Odoo to raise a Purchase Order (PO) to send to the supplier for the cost of manufacturing.

Can Odoo be configured to create the Purchase Order for cost of manufacturing.

Avatar
Discard
Related Posts Replies Views Activity
0
Mar 15
5053
2
Aug 25
649
2
Mar 25
3434
0
Jan 25
1050
2
Aug 24
4280