I create a request for quotation and receive a delivery date from the supplier, e.g. in 6 weeks. I confirm the enquiry with the specified delivery date. A week later, the supplier contacts me and informs me of a new delivery date, a delay of two weeks.

If I update this date in the order, the old date is still displayed as the expected date in both the warehouse for planned receipts and in manufacturing.


How can I get the date to update so that manufacturing can plan with the new date?


Avatar
Discard

Hello Thomas,

Same issue here. Did you get meanwhile a solution for the problem?

Best Answer

Update the date of the Receipt instead. The Purchase Order is a "contract" with your Vendor and should not be changed after being confirmed and issued to the Vendor.