Skip to Content
Menu
You need to be registered to interact with the community.
This question has been flagged
1 Odgovori
2458 Prikazi

I create a request for quotation and receive a delivery date from the supplier, e.g. in 6 weeks. I confirm the enquiry with the specified delivery date. A week later, the supplier contacts me and informs me of a new delivery date, a delay of two weeks.

If I update this date in the order, the old date is still displayed as the expected date in both the warehouse for planned receipts and in manufacturing.


How can I get the date to update so that manufacturing can plan with the new date?


Avatar
Opusti

Hello Thomas,

Same issue here. Did you get meanwhile a solution for the problem?

Best Answer

Update the date of the Receipt instead. The Purchase Order is a "contract" with your Vendor and should not be changed after being confirmed and issued to the Vendor.

Avatar
Opusti
Related Posts Odgovori Prikazi Aktivnost
1
apr. 24
1622
0
avg. 25
482
4
maj 25
2910
2
maj 25
6337
1
mar. 25
1957