Hi,

After using odoo 10 with mrp for a while we decided to implement the next step routing which is quite straight forward.

But in some of the tutorials you see "assembly station 1 " , "assembly station 2 " etc.
We actually have no idea up front through which assembly station the routing goes. 
(in our definition a workcenter is an assembly station where 1 person works, so all the assembly stations could do the same type of work: assemble furniture)

So how do you handle these situations/ or how do you configure it? 
does each person has it own WC or do they use it like a group?
If handled like a group how do you allocate the resources (we have a basic group of employees and contractors that come and go when we have projects)

thanks
Avatar
Discard

I'm on Odoo 12 ad facing the same issue as well. Anyone care to share the best practice for this type of situation?