Hello!
In v15 how can we update the process bar in the tasks in the project?
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
Hello!
In v15 how can we update the process bar in the tasks in the project?
Hello
You should set “Allocated Hour” to a task, when an employee spent hours in a task the progress bar will update.
The progress bar represents the hours completed from
“Allocated Hour”.
Thank you for the reply!
But I want to do progress update by the task only. I have no requirement to timesheet the task. So the project is created with no timesheet feature.