Hello!

In v15 how can we update the process bar in the tasks in the project?

頭像
捨棄
最佳答案

Hello

You should set “Allocated Hour” to a task, when an employee spent hours in a task the progress bar will update.

The progress bar represents the hours completed from  “Allocated Hour”.


頭像
捨棄
作者

Thank you for the reply!
But I want to do progress update by the task only. I have no requirement to timesheet the task. So the project is created with no timesheet feature.