Whenever I created a new task, it always set in undefined project stage.

Anyone knows how to define the first stage by default when a task created?

Avatar
Discard
Best Answer

You can create new stages.

image description

image description

In the above screenshot

define stage name, related status, sequence number is must.

please check the Default for New Projects checkbox for occuring this stage is default for all projects or wanted projects.

Avatar
Discard
Author

Thanks for your help. But that's not what I meant. Whenever I create a new task, it will be placed in undefined stage instead of my-already-define stages.

i cant see your picture

Please edit Related Status as NEW

Author Best Answer

image description

this is the In Progress stage screen-shot image description

as the picture above, when i create a new task, it automatically set to undefined stage. how it can be set to in-progress stage by default?

Avatar
Discard

i cant see your picture

Author

sorry, i saved the pic as the tiff type. can you see it now?

please send a screenshot of In progress stage.

Author

sent at the picture above

Please edit Related Status as NEW

Author

It's done! Thank you very much! :)

Best Answer

In order to do that, you need to set the "Related status" of your "Stage Name" to "New".

After that, the stage name of your newly created task will automatically be setted to the "Stage Name" you define as "New", in your case, "In progress"

Avatar
Discard
Best Answer

Hi, I'm using odoo 10,
Icannot find default for new project in stage.


please help

Avatar