Whenever I created a new task, it always set in undefined project stage.

Anyone knows how to define the first stage by default when a task created?

Awatar
Odrzuć
Najlepsza odpowiedź

You can create new stages.

image description

image description

In the above screenshot

define stage name, related status, sequence number is must.

please check the Default for New Projects checkbox for occuring this stage is default for all projects or wanted projects.

Awatar
Odrzuć
Autor

Thanks for your help. But that's not what I meant. Whenever I create a new task, it will be placed in undefined stage instead of my-already-define stages.

i cant see your picture

Please edit Related Status as NEW

Autor Najlepsza odpowiedź

image description

this is the In Progress stage screen-shot image description

as the picture above, when i create a new task, it automatically set to undefined stage. how it can be set to in-progress stage by default?

Awatar
Odrzuć

i cant see your picture

Autor

sorry, i saved the pic as the tiff type. can you see it now?

please send a screenshot of In progress stage.

Autor

sent at the picture above

Please edit Related Status as NEW

Autor

It's done! Thank you very much! :)

Najlepsza odpowiedź

In order to do that, you need to set the "Related status" of your "Stage Name" to "New".

After that, the stage name of your newly created task will automatically be setted to the "Stage Name" you define as "New", in your case, "In progress"

Awatar
Odrzuć
Najlepsza odpowiedź

Hi, I'm using odoo 10,
Icannot find default for new project in stage.


please help

Awatar
Odrzuć
Powiązane posty Odpowiedzi Widoki Czynność
0
mar 17
3049
1
mar 15
10019
1
lip 19
5843
5
sty 17
5447
1
cze 23
3362