Skip to Content
Menu
This question has been flagged
1166 Views

I have a MO scheduled to be made in one week. On that MO I have a sub BOM that only takes a day to make. But in that sub BOM are purchased components that have a lead time of 45 days.

Currently, I have no visibility that I need to order the components. I think this is due to Odoo not wanting to make the sub BOM until it is needed so there is not yet any demand for the component. But it will cause a problem when the MO is created because then I will have to wait 45 days for the component to be ordered get delivered.  Scheduler has been ran.

 
Any thoughts on how to handle it?


Avatar
Discard
Related Posts Replies Views Activity
2
Aug 22
3101
1
Mar 22
1603
1
Feb 22
1340
1
Feb 22
1656
4
Aug 24
2404