This question has been flagged
2838 Views

I have a MO scheduled to be made in one week. On that MO I have a sub BOM that only takes a day to make. But in that sub BOM are purchased components that have a lead time of 45 days.

Currently, I have no visibility that I need to order the components. I think this is due to Odoo not wanting to make the sub BOM until it is needed so there is not yet any demand for the component. But it will cause a problem when the MO is created because then I will have to wait 45 days for the component to be ordered get delivered.  Scheduler has been ran.

 
Any thoughts on how to handle it?