Skip to Content
Menu
Musisz się zarejestrować, aby móc wchodzić w interakcje z tą społecznością.
To pytanie dostało ostrzeżenie
2195 Widoki

I have a MO scheduled to be made in one week. On that MO I have a sub BOM that only takes a day to make. But in that sub BOM are purchased components that have a lead time of 45 days.

Currently, I have no visibility that I need to order the components. I think this is due to Odoo not wanting to make the sub BOM until it is needed so there is not yet any demand for the component. But it will cause a problem when the MO is created because then I will have to wait 45 days for the component to be ordered get delivered.  Scheduler has been ran.

 
Any thoughts on how to handle it?


Awatar
Odrzuć
Powiązane posty Odpowiedzi Widoki Czynność
2
sie 22
4780
1
mar 22
2578
1
lut 22
2391
1
lut 22
2901
4
sie 24
3897