Hello,

When an employee submits his timesheet, the manager recieves it and checks it and if okay he approves it or refuses it. My question is, when a manager is checking a timesheet and he finds out it's not okay, can I modify the timesheet as a manager and after that still approve it?

Avatar
Discard
Best Answer

You are not allowed to modify a confirmed/submitted timesheet. You first have to refuse it.

This makes sense since otherwise the manager could change figures without the notice of the employee.

Avatar
Discard
Author Best Answer

Thank you, I get it now.