With Odoo how we can manage our production capacity in order to give correct delivery date to our customer
Exemple
I have 1 work center capable to produce 1 unit per day .
I get one customer how asked me to buy 1 unit , MO is created and scheduled to be delivered tomorrow (Good Ok)
In the same day an other customer how asked me for 2 units.
Odoo create the second MO and show to me that he will be produced after 3 days
But he will be delivered tomorrow also !! (which is worrong as the MO he will be finished only after 3 days )
What is best configuration or modules that allow me to correctly calculate the correct delivery date based on my production capacity ?
I want to get this information on my sale orders before planning the prodcution as my customer want this information and also it's not visible to my sales person , he don't have access the the manufacturing module and he don't know the right production date ?
How Odoo manage this kind of cases ?