I created a MO which generated a WO. 

We are trying to track time for the WO. The assembler accidentally hit "Mark As Done" right away. 

I would like to change the state of the WO back to in progress. But I can't seem to find a way to do that.

Any suggestions would be wonderful. Thank you!

odoo12sh

Avatar
Zrušiť
Autor

I know that I can just complete the MO and then do a manual Inv adjustment. And then generate a new MO/WO But that seems like a roundabout way to get this accomplished.

Best Answer

You cannot change the state, but you can change the WO duration manually (change the start and end date and time)

BR

Ricardo

Avatar
Zrušiť
Autor

Thanks, Richard I guess I could do that as well. Have them manually track it and then add that to the WO at the end.

I just was hoping there was an "Undo" button