Hi, how can I hide a sub-task in kanban view

I need view a sub task only in the task details

regards

Avatar
Discard
Author

 great, amazing how sometimes things are in sight and we don't see them.
Thank you very much.

Best Answer

Hello, Johnny!

You can set the filter: *Parent Task > is not set*.

Another option would be to create a specific project for sub-tasks :)

Have a great day!

Cheers,

Odoo eLearning Team.