 Hello

The only way seems in V12 is to setup different BOM with Different routing.

But We have the option of 'Alternative work-centre'  in our latest version-13.In which you can manage to perform the same operation in different WCs. You just need to setup the 'Alternative WC' in your main WC settings and the system will automatically plan your next order to that WC if main WC is busy in another operation.

Thanks.