On V13 what is the simplest method for correcting a supplier payment accidentally allocated to the wrong supplier?

Avatar
Discard
Best Answer

If the payment already reconciled with a bill, You have to unreconcile it and then from payment screen click on "Reset to Draft" button, this will set the payment to draft so you can change the vendor and then reconcile it with the correct bill.