Hello

When I request 1 day of holiday, the system counts 0.75 unit of holiday.

When I request 2 days, it counts 1.75 unit.

I cannot request on a specific time of the day.

But when the manager requests if for the employee, the unit is full (1 or 2).

My version is 12

Any idea?

Thanks

Avatar
Discard
Best Answer

Hi, 

Please check timezone in scheduled working hours and log in user's timezone in user preference are set as same, if it's different it shows difference in interval. 

Also Make sure Scheduled working hours are also correct. 

Hope it Helps, 

Kiran K

Avatar
Discard
Author Best Answer

Hey

Thanks so much Kiran. Issue is solved ! 

Regards 