Hi all,

I am working with odoo v.14, and I have to write the hours spent on each timesheets of each task I am assigned to. I need to control if my total participation is equal to a certain amount of hours weekly. I know that there are filters to do that, but could you guide me to use it, please?

Again, thanks for your help,
have a nice day

Avatar
Discard
Author

Hi all, I've been able to see my weekly tasks well organized using the odoo timesheet module from the menu. I could see in list all the tasks I did with the number of hours assigned under my name, using existing filters.
But, I had a bug: One task had the time running (this little kind of "play button" open) and I ended up with a huge incorrect amount of hours regarding this particular task.
So, what I did was: stop the running task, and enter a correct time for it. But the weekly amount of hours above still shows the incorrect previous total saved hours, unfortunately.
Any idea of how could I correct this? Thanks again for helping

Author Best Answer

Thanks a lot for your answer, I think that in fact I already use the task itself by clicking on Edit, entering the hour on a new line of the timesheet tab and Save. But how can I display a project overview with my name filtered, please?

Avatar
Discard
Best Answer

Hi, 

If you prefer, instead of enter the hours through the timesheet app, you can do it through the project app.

Click on the project -> task ->  timesheet tab -> edit and enter your hours directly on the task.

Then if you need a report you can go to the project overview and you can see your hours by task.

 

Avatar
Discard
Author

Hi, thanks a lot for your answer but I still couldn't manage to make this. I couldn't find the projects overview and filter my name to display my daily or weekly hours assigned on tasks, could you help me do that, please? I need to mention that I am not the project's creator, if that has an impact, Have a great day