any help on this will be so grateful. I have a project that has 17 tasks, now I have 10 more projects that need the same tasks. How to do I copy tasks from 1 project to another?
Odoo is the world's easiest all-in-one management software.
It includes hundreds of business apps:
- CRM
- e-Commerce
- Accounting
- Inventory
- PoS
- Project management
- MRP
This question has been flagged
You can copy the entire project 10 times. Would that save you time?
You can consider some projects 'templates' that contain the tasks that your different project types will always have by default, then copy then. I keep these projects archived so they don't show up when looking for 'real' projects.
EDIT
To do this:
1. Project --> Configuration --> Projects
2. Open the Project you want to copy.
3. From the Action Menu, choose DUPLICATE
Hi Ray,
How do you do to copy an entire project?
I am using Odoo 10 CE.
Thanks
See my edit.
Thank you. New to this, as you can tell.