Câu hỏi này đã bị gắn cờ
3 Trả lời
7002 Lượt xem

any help on this will be so grateful. I have a project that has 17 tasks, now I have 10 more projects that need the same tasks.  How to do I copy tasks from 1 project to another? 


Ảnh đại diện
Huỷ bỏ

Thank you. New to this, as you can tell.

Câu trả lời hay nhất

You can copy the entire project 10 times.   Would that save you time? 

You can consider some projects 'templates' that contain the tasks that your different project types will always have by default, then copy then.  I keep these projects archived so they don't show up when looking for 'real' projects.


EDIT

To do this:

1. Project --> Configuration --> Projects

2. Open the Project you want to copy.

3. From the Action Menu, choose DUPLICATE


Ảnh đại diện
Huỷ bỏ
Câu trả lời hay nhất

Hi Ray,

How do you do to copy an entire project?

I am using Odoo 10 CE.

Thanks

Ảnh đại diện
Huỷ bỏ

See my edit.

Bài viết liên quan Trả lời Lượt xem Hoạt động
0
thg 2 24
1725
2
thg 10 23
1915
Project and Tasks Đã xử lý
1
thg 7 23
2118
2
thg 6 20
5552
0
thg 8 15
4162