Odoo Help

Welcome!

This community is for beginners and experts willing to share their Odoo knowledge. It's not a forum to discuss ideas, but a knowledge base of questions and their answers.

1

Activity and human resource, GANTT question...

By
Marco Baldocchi
on 1/29/16, 5:28 AM 497 views

hello,

i've this problem:

i created a project, and an activity. My emplyee have to work 48 hours in 3 weeks (two days a week).

I insert start and end date and 48 hours but in GANTT i see as my emplyee works 3 weeks at that project and not only 2 days a week.

How i can solve?

Your Answer

Please try to give a substantial answer. If you wanted to comment on the question or answer, just use the commenting tool. Please remember that you can always revise your answers - no need to answer the same question twice. Also, please don't forget to vote - it really helps to select the best questions and answers!

About This Community

This community is for professionals and enthusiasts of our products and services. Read Guidelines

Question tools

1 follower(s)

Stats

Asked: 1/29/16, 5:28 AM
Seen: 497 times
Last updated: 1/29/16, 5:39 AM