hello,

i've this problem:

i created a project, and an activity. My emplyee have to work 48 hours in 3 weeks (two days a week).

I insert start and end date and 48 hours but in GANTT i see as my emplyee works 3 weeks at that project and not only 2 days a week.

How i can solve?