I would like to know how to set up procurement rules for the following situation:
1. Manufacturing a "Product" that consists of a "Part" with a single vendor with the delivery lead time of 10 days.
2. I will set up manufacturing for 1st week of June '18, 1st week of Sept '18 a' 50pcs
I would like to get 2 procurements (one in mid-June and one in mid-August) with 50pcs each
Currently, I cannot achieve this with either procurement rules or MTO, please help...