Hi,


I didn't get any solution to my problem

I want to give a detail explanation then you can easily understand what is my problem exactly. 

First I created 4 products.

  •  Product 1-"Rod" with routes -Buy,Replenish on Order (MTO),Resupply Subcontractor on Order

  •  Product 2- "Rod_Milling" with same above routes

  •  Product 3- "Rod_Drilling" with same above routes

  •  Product 4- "Rod_Finished" with Route - Buy

The vendors for above 4 Products are different as well as prices are different.

Now I created bill of material for Product 4 only (product 4 BOM consists of product 1,2&3).

Now I created MO for 1 Assembly consists of Product 4 BOM

If I run the" Run Scheduler " then RFQ's are automatically generated 

Here the problem occurred that is RFQ directly generated to product 4, if that RFQ is confirmed (Purchase Order) then RFQ generated for product 3 , and the process goes on.  Finally  I got the RFQ for product 1.

This example shows that the RFQ generation  process is in reverse order.

We didn't required like that.

Now I required a solution for generating RFQ's in a sequential  manner with Tentative Schedule dates 

  This process occurred in Odoo 13 Community version