Hi,
I didn't get any solution to my problem
I want to give a detail explanation then you can easily understand what is my problem exactly.
First I created 4 products.
Product 1-"Rod" with routes -Buy,Replenish on Order (MTO),Resupply Subcontractor on Order
Product 2- "Rod_Milling" with same above routes
Product 3- "Rod_Drilling" with same above routes
Product 4- "Rod_Finished" with Route - Buy
The vendors for above 4 Products are different as well as prices are different.
Now I created bill of material for Product 4 only (product 4 BOM consists of product 1,2&3).
Now I created MO for 1 Assembly consists of Product 4 BOM
If I run the" Run Scheduler " then RFQ's are automatically generated
Here the problem occurred that is RFQ directly generated to product 4, if that RFQ is confirmed (Purchase Order) then RFQ generated for product 3 , and the process goes on. Finally I got the RFQ for product 1.
This example shows that the RFQ generation process is in reverse order.
We didn't required like that.
Now I required a solution for generating RFQ's in a sequential manner with Tentative Schedule dates
This process occurred in Odoo 13 Community version