example:

I have two assemblies that can be MTO: ASM1 and ASM2.  Both of these assemblies use a component COMP1.

COMP1 has an MOQ of 300 pcs.

If I create a manufacturing order for 100 ASM1, I get a draft purchase order for 300 COMP1 as expected/desired.

However, if I create a manufacturing order for 100 ASM1 and 100 ASM2, then I get a draft purchase order for 600 COMP1, not 300.  The MOQ for COMP1 gets doubled for each ASM.  Is there any way to fix this? If not, then I just have to go into all the purchase orders and edit them manually, which doesn't save me the intended amount of time.

Any help is appreciated. 

Thank you!

Avatar
Discard

Hi Sara, If I am not wrong, are you looking Product Bundling kind of thing