I must manage events such way that when the event is near (eg within ten days of its commencement) I notify users, can someone help me

Avatar
Discard
Best Answer

Read the response to this question.

And for the Related Document Model choose Event, and for the Trigger Date select Start Date and - X Days for Delay After Trigger Date.

Where X is the number of days before (with minus) the start date.