Hello All
steps to reproduce:
- Configure Manufacturing product with a manufacturing lead time of 1 day(Manufacture)(work center-working schedule -8 Hours/day)
BOM components are available in stock - Assign the Working Time entry to Workcenter with 1200 minutes(2.5 days)
- ISSUE: Create a sales order with 1 unit of the finished product unavailable in stock. Now, based on the MO Forecasted date, we will set our delivery date..for example, If I create a Sales order on 10th April and check the MO forecast date will be 11th April with 1 day lead time. based on that we will set our delivery date 11th April.
- when we do actual manufacturing it will take 2.5 days to manufacture
- so our delivery will be delayed in this case
- ISSUE: How can we commit to the right delivery date here by checking the MO forecasted date?