Dear Odoo'ers 


I would like to set up a process that when I confirm a Purchase order, odoo automatically manufactures the products (so raw materials will be deducted, and ready product will be added). All BOM's are set up. 


Up until now, I have tried multiple subcontracting routes, but they did work work. Also tried MTO, but that only triggers with a Sales order. 


Is there somebody that could help me? 


Cheers! 

 

Avatar
Discard
Best Answer

Believe you are referring to sub contracting process, where a PO initiates the process. Material/ component consumption is recorded in the receipt operation.

The tutorial details the steps. 
https://www.odoo.com/slides/slide/subcontracting-resupply-vendors-2859?fullscreen=1

Avatar
Discard
Best Answer

Hi Leroy,

What will happen to the Purchase Order? how will it be fullfilled?

Regards,

Hamid - bitigloo GmbH

Avatar
Discard