Hi,
I have found a very odd behavior scheduler in Odoo 14 enterprise.
I have a product with a vendor leadtime, lets say 10 days. Also I have set a Reordering Rule for that product which creates an RFQ with delivery time 10 days. All fine so far.
But if I want to receive the product later than 10 days, I will change Receipt Date >10days. This is basically the situation for all purchases now as delivery times have increased for raw materials. After confirming RFQ -> PO, scheduler will now create a new RFQ for the same product, again with leadtime 10 days since that is what is still the leadtime set on the product.
This results in a lot of duplicates RFQ's since there is already an ongoing PO.
Can this be configured somehow? Or does anyone have any other idea how I can deal with this issue.
Regards,
Rickard