Hi,

I have found a very odd behavior scheduler in Odoo 14 enterprise.

I have a product with a vendor leadtime, lets say 10 days. Also I have set a Reordering Rule for that product which creates an RFQ with delivery time 10 days. All fine so far.

But if I want to receive the product later than 10 days, I will change Receipt Date >10days. This is basically the situation for all purchases now as delivery times have increased for raw materials. After confirming RFQ -> PO, scheduler will now create a new RFQ for the same product, again with leadtime 10 days since  that  is  what is  still  the leadtime set on the product.


This results in a lot of duplicates RFQ's since there is already an ongoing PO. 


Can this be  configured somehow? Or  does  anyone  have  any  other  idea  how  I  can  deal  with  this  issue.


Regards,
Rickard

Avatar
Discard
Best Answer

So if a vendor updates it's delivery time for a product later than what we expected initially, Odoo ask you to buy it again, from the same vendor to solve the problem. 

And this is expected behaviour? What is the logic behind this?

Avatar
Discard

Odoo logic is that when you order again, this time the vendor will deliver on time, so your problem is solved!!

I tried logging this as a bug on GitHub, but all that happens is more Odoo users confirm that this is what is happening.