I am using Odoo8, and here is my scenario -

1. 3 step shipping

2. Using a MTO/MTS community module to choose what procurement rule applies when in case of MTO or MTS?

3. In case of MTO > I create an MO

4. When an MO is created, system should create a procurement from stock to production staging location as per my routing on the raw materials.

5. But it not doing so, moreover the supply method is always take from stock...

Please help. I want system to create a procurement for raw materials and draw it from inventory it is already there otherwise create a PO.

About This Community

This platform is for beginners and experts willing to share their Odoo knowledge. It's not a forum to discuss ideas, but a knowledge base of questions and their answers.

Register

Odoo Training Center

Access to our E-learning platform and experience all Odoo Apps through learning videos, exercises and Quizz.

Test it now

Question tools

1 follower(s)

Stats

Asked: 5/5/16, 9:21 AM
Seen: 672 times
Last updated: 5/5/16, 9:41 AM