MO 'capacity' modification - enforce maximum number that can be made

By
Ray Carnes
on 10/16/13, 5:44 PM 678 views

Has anyone modified MRP to take into account maximum amounts of finished products than can be produced in a single run due to production constraints?

Example:

A company can only produce 1000 items at once. The scheduler determines 1,500 are needed.

What happens now:

One MO is created: MO1 - 1,500.

What I want to happen:

Two MO's are created: MO1 - 1,000 and then MO2 - 500.

Currently, users are manually duplicating MO's or manually changing the quantity down to the limit and letting the scheduler re-create what is outstanding as a giant MO that also then needs to be changed.

Your Answer

Please try to give a substantial answer. If you wanted to comment on the question or answer, just use the commenting tool. Please remember that you can always revise your answers - no need to answer the same question twice. Also, please don't forget to vote - it really helps to select the best questions and answers!

About This Community

This community is for professionals and enthusiasts of our products and services. Read Guidelines

Question tools

0 follower(s)

Stats

Asked: 10/16/13, 5:44 PM
Seen: 678 times
Last updated: 3/16/15, 8:10 AM